Business documents

How to write a change order

What a construction change order contains, how to calculate the new contract sum and time, and a worked example following the structure of the AIA G701 form.

Contractor and homeowner reviewing building plans on a work table at a renovation site

In short

  • A change order records an agreed change to the original contract: what changes, what it costs, and how it affects the schedule.
  • The money section follows a chain: original contract sum, net change by previous change orders, sum before this change, this change, new contract sum.
  • State the change in contract time (for example +3 working days) and the new completion date if it moves.
  • Both parties sign before the extra work starts (on AIA projects, the architect signs as well).

Almost every building project changes along the way. The client adds an outlet, picks a different tile, or the crew finds rot behind a wall. A change order puts each change in writing before the work is done, so the price and schedule never depend on memory.

In the US, the AIA G701 form is a widely used standard for this. The structure below follows it, and works just as well for small residential jobs.

What a change order contains

  1. Project and contract. Project name and address, contract date, the parties, and the change order number (CO-001, CO-002, …).
  2. Description of the change. What is added, removed or substituted, specific enough that someone else could price it. Refer to drawings or specification sections where they exist.
  3. Reason, briefly: client request, unforeseen condition, design change.
  4. Cost. Line items for labor, materials and equipment, or one agreed amount.
  5. Contract sum chain, explained below.
  6. Contract time. The change in days and, if it moves, the new completion date.
  7. Signatures of the owner and the contractor (and the architect on AIA contracts), with dates.

The contract sum chain

The money section always runs in the same order. AIA’s G701 lays it out like this:

Line Meaning
Original contract sum The price in the signed contract
Net change by previously authorized change orders All earlier change orders added together; negative if they removed work
Contract sum prior to this change order Original sum + previous changes
Increase or decrease by this change order The amount of this change
New contract sum including this change order Prior sum + this change

As Procore notes, the “prior” figure should equal the new contract sum on the previous change order. On the first change order, the previous changes are zero. Changes made by a construction change directive are left out until they are agreed and recorded in a change order.

Worked example

A bathroom remodel was contracted at $48,000. Change order 1 added heated floors for $2,500. Now the client wants a second vanity and a recessed niche.

Amount
Original contract sum $48,000.00
Net change by previous change orders (CO-001) + $2,500.00
Contract sum prior to this change order $50,500.00
This change order (CO-002): second vanity, plumbing and niche + $3,200.00
New contract sum $53,700.00
Change in contract time + 3 working days

The next change order, CO-003, starts from $53,700 as its “prior” sum, with $5,700 as the net change by previous change orders.

Pricing the change

Clients accept a change order more readily when they can see how the number was built. For CO-002 above, the $3,200 could break down like this:

Line Calculation Amount
Plumber: second drain and supply lines 6 h × $85 $510.00
Carpenter: vanity install, niche framing 10 h × $65 $650.00
Tile setter: niche waterproofing and tile 5 h × $70 $350.00
Vanity, faucet and fittings as quoted by supplier $1,180.00
Waterproofing kit, tile, trim $230.00
Subtotal $2,920.00
Overhead and profit at the contract rate (here about 9.6%, rounded) $280.00
This change order $3,200.00

Use the labor rates and markup written in your contract, if it has them. If it does not, agree them before the first change order. A rate negotiated in the middle of a disagreement is always harder.

When a change removes work

Change orders can lower the price too. If the client decides to supply their own light fixtures, which the contract priced at $400 including installation materials, the change order shows a decrease:

Amount
Contract sum prior to this change order $53,700.00
CO-003: owner-supplied light fixtures, deduct fixtures − $400.00
New contract sum $53,300.00

The net change by previous change orders on CO-004 would then be +$5,300 ($2,500 + $3,200 − $400). Record credits as carefully as extras. A contract that only ever goes up looks worse to a client than one where they can see the deductions too.

When you open a wall and find a problem

Hidden conditions are the most common source of disputes, because the work often has to continue quickly. A routine that protects both sides:

  1. Stop work on the affected part, if it is safe to do so.
  2. Photograph what you found, with something for scale, and note the date.
  3. Tell the owner the same day, in writing, with the photos.
  4. Price it as a change order, or as a time-and-materials allowance with a cap if the extent is not yet known.
  5. Get a signature before continuing, even if it is a signed PDF or a reply to an email.

Keep a change order log

A one-page log answers most questions about the job at a glance:

CO Date Description Amount Days Status
CO-001 Mar 4 Heated floor, main bathroom + $2,500 0 Signed
CO-002 Mar 18 Second vanity and shower niche + $3,200 + 3 Signed
CO-003 Mar 25 Owner-supplied light fixtures − $400 0 Signed
Total + $5,300 + 3

Habits that prevent disputes

  • One change per change order, or a few closely related ones. It keeps approvals fast.
  • Number them in order and keep a log with the running total.
  • Price time as well as money. A change that adds no cost but three days still changes the contract.
  • Sign before you build. If the owner is away, a signed PDF by email is far better than a verbal “go ahead”.
  • Invoice against the new sum. The next invoice or payment application should use the updated contract sum.

Frequently asked questions

Who writes the change order?

Usually the contractor prepares it, because they price the work, and the owner (and the architect, where the contract names one) reviews and signs it. On some projects the owner's side prepares it.

What is the difference between a change order and a change directive?

A change order is signed by both parties, so price and time are agreed. A construction change directive (AIA G714) lets the owner order a change before price or time are agreed. It becomes part of a change order only once everyone agrees.

Can a change order reduce the price?

Yes. Removing work produces a deductive change order with a negative amount, and the new contract sum goes down.

Should I do the extra work before the change order is signed?

It is safest not to. Unsigned extras are the most common source of payment disputes. If work must start urgently, get at least a written instruction and price it as soon as possible.

Sources

  1. Instructions: G701–2017, Change Order, AIA Contract Documents help center
  2. Guide to the AIA G701 change order, Procore
  3. Guide to the AIA G701 change order, Trimble

Photos are AI-generated illustrations; diagrams and tool screenshots are made from the PlanPrint tools. Something out of date or wrong? Tell us and we will correct it.

Related guides