Shift schedules

12-hour shift schedules compared: DuPont, 2-2-3 and 4 on 4 off

DuPont, 2-2-3 (Pitman and Panama) and 4 on 4 off side by side: cycle length, longest stretch of shifts, days off and weekends, with charts for all four crews.

Night shift operator watching monitoring screens in an industrial plant control room

In short

  • All three are 4-crew, 12-hour schedules that cover 24/7. Each crew averages 42 hours a week, about 182 shifts and 2,190 hours a year.
  • DuPont: 28-day cycle with up to 4 shifts in a row and one 7-day break per cycle.
  • 2-2-3: 14-day cycle, never more than 3 shifts in a row, every other weekend off (Friday to Sunday).
  • 4 on 4 off: 8-day cycle, 4 shifts then 4 days off; the days move through the week, so 3 of every 8 weekends are fully off.
  • Names are used loosely. Pitman and Panama both refer to 2-2-3 variants; check your employer's exact rotation.

Four crews, two 12-hour shifts a day, every day of the year: that is the setting for the three most common 12-hour rotations. The rotation charts below are generated by the same engine as our shift calendar, and the figures in the comparison table were calculated by it. They match the patterns published by the sources at the end of this guide.

The comparison

DuPont 2-2-3 (Pitman) 4 on 4 off
Crews 4 4 4
Cycle length 28 days 14 days 8 days
Most shifts in a row 4 3 4
Longest break 7 days 3 days 4 days
Days and nights Rotate within the cycle Fixed, or rotating every 2 or 4 weeks Fixed, or rotating
Full weekends off Depends on where the cycle starts Every other weekend (Fri–Sun) 3 of every 8
Average per week 42 h 42 h 42 h
Per year 182.5 shifts, 2,190 h 182.5 shifts, 2,190 h 182.5 shifts, 2,190 h

The yearly figures are the same because they have to be: four crews share 730 twelve-hour shifts a year (365 days × 2 shifts), so each crew works a quarter of them.

DuPont

The DuPont schedule runs over 28 days: 4 nights, 3 days off, 3 day shifts, 1 day off, 3 nights, 3 days off, 4 day shifts, then 7 days off. That adds up to 14 shifts, or 168 hours, every four weeks: 42 hours a week on average.

1M2T3W4T5F6S7S8M9T10W11T12F13S14S15M16T17W18T19F20S21S22M23T24W25T26F27S28SANNNNDDDNNNDDDDBNNNNDDDNNNDDDDCDDDDNNNNDDDNNNDDDDNNNDDDDNNNN

Day shiftNight shiftOff

DuPont schedule: one full 28-day cycle. Each row is a crew; columns are days starting on a Monday.

The draw is the seven-day break once every four weeks: a real holiday without using vacation days. The cost is the quick turnaround in the middle of the cycle, where three day shifts are followed by a single day off before three nights, and the stretches of four 12-hour shifts in a row.

DuPont schedule calendar →

2-2-3 (Pitman and Panama)

The 2-2-3 pattern repeats every 14 days: 2 on, 2 off, 3 on, 2 off, 2 on, 3 off. Nobody works more than three shifts in a row, and every other weekend is a three-day weekend from Friday to Sunday.

1M2T3W4T5F6S7S8M9T10W11T12F13S14SADDDDDDDBDDDDDDDCNNNNNNNDNNNNNNN

Day shiftNight shiftOff

2-2-3 with fixed shifts: crews A and B work days, C and D work nights. One full 14-day cycle starting on a Monday.

In the fixed version, two crews stay on days and two stay on nights. In rotating versions, crews swap between days and nights every two or four weeks. This is where the names get confusing: many sources call the fixed version Pitman and the rotating one Panama, but workplaces are not consistent. Compare the actual pattern with your roster rather than relying on the name.

2-2-3 schedule · Pitman schedule · Panama schedule

4 on 4 off

The simplest pattern: four shifts, then four days off, repeating every eight days. Because 8 does not divide into a 7-day week, your days on move one day later each week, so they cover every weekday in turn. Over 8 weeks, 3 weekends are fully off.

1M2T3W4T5F6S7S8M9T10W11T12F13S14S15M16TADDDDDDDDBDDDDDDDDCNNNNNNNNDNNNNNNNN

Day shiftNight shiftOff

4 on 4 off with fixed shifts, shown over 16 days: crews A and B work days, C and D nights. Notice how the block moves through the week.

The steady rhythm is easy to remember and plan around. The four-shift blocks are long, and the moving days off make regular weekly activities (a class every Tuesday, for example) harder to keep.

4 on 4 off calendar →

Hours per week are not 42 every week

All three average 42 hours, but no single week is “average”. With the cycle starting on a Monday, the weeks look like this:

Schedule Week 1 Week 2 Week 3 Week 4
DuPont 4 nights = 48 h 3 days + 3 nights = 72 h 4 days = 48 h off = 0 h
2-2-3 5 shifts = 60 h 2 shifts = 24 h 5 shifts = 60 h 2 shifts = 24 h
4 on 4 off 3 or 4 shifts each week: 36 or 48 h, moving with the cycle

This matters for pay. In the US, the Fair Labor Standards Act requires overtime for most hourly employees for hours over 40 in a workweek, so a schedule that averages 42 hours still produces overtime in its long weeks, and none in the short ones. How much that adds up to depends on how your employer defines its workweek and on your contract or union agreement. Ask payroll rather than estimating it from the average.

Days, nights and sleep

Schedule Night shifts per cycle Switches between days and nights
DuPont 7 of 14 shifts Within every cycle, including a quick change mid-cycle
2-2-3, fixed All or none, depending on your crew Never
2-2-3, rotating Half, in blocks of 2 or 4 weeks Every 2 or 4 weeks
4 on 4 off, fixed All or none Never

Fixed shifts avoid repeated switches between day and night sleep, but they leave some crews on permanent nights. Rotating versions share the nights fairly and ask everyone to adjust regularly. NIOSH’s training material on shift work describes the trade-offs of fast and slow rotation and notes that researchers cannot recommend a single best design. See what is a rotating shift for the details.

Reading your own roster

If your roster only shows “D”, “N” and “O” for a few weeks, you can still identify the pattern:

  1. Count the length of the repeating block. 28 days points to DuPont, 14 days to 2-2-3, 8 days to 4 on 4 off.
  2. Look for the longest break: 7 days off is the DuPont signature.
  3. Check the longest stretch on: no more than 3 in a row suggests 2-2-3.

Then enter the pattern and your crew in the shift calendar and compare its first month with your roster. If they match, the rest of the year will too.

Which one is best?

That depends on what you value more:

  • Long breaks: DuPont’s 7-day break.
  • Short stretches and regular weekends: 2-2-3.
  • A rhythm that is easy to remember: 4 on 4 off.

For shift workers, the practical question is usually not which pattern to pick, but what the one you were given means for your year. Put it on a calendar, check holidays and family dates, and add it to your phone so you never have to count days again.

Frequently asked questions

Which 12-hour schedule has the most days off?

None. Every 4-crew, 12-hour schedule that covers 24/7 gives each crew the same average: half the days on, half off, 42 hours a week. They differ in how the days off are grouped.

What is the difference between Pitman and Panama?

Both are 2-2-3 patterns (2 on, 2 off, 3 on, 2 off, 2 on, 3 off). In many workplaces, Pitman means crews stay on days or nights, while Panama is often used for the version where crews rotate between days and nights. Employers use the names differently, so compare the actual pattern.

Do these schedules include overtime?

A 42-hour average week is above 40 hours, so some weeks may include overtime under the rules that apply to you, depending on how your employer defines the work week. Your contract and local law decide this, not the schedule name.

Is a rotating schedule worse than fixed days or nights?

It is a trade-off. Rotation shares nights fairly across all crews; fixed shifts let people keep a steady sleep pattern. Which suits a crew better is often a matter of individual sleep patterns and family life.

Sources

  1. NIOSH Training for Nurses on Shift Work and Long Work Hours, Module 5: Work schedule design, National Institute for Occupational Safety and Health (CDC/NIOSH)
  2. Overtime pay, U.S. Department of Labor, Wage and Hour Division
  3. DuPont shift scheduling, TimeTrex
  4. DuPont schedule, Clockify
  5. 2-2-3 schedule (Panama) and Pitman schedule, Soon
  6. Pitman schedule, Everhour

Photos are AI-generated illustrations; diagrams and tool screenshots are made from the PlanPrint tools. Something out of date or wrong? Tell us and we will correct it.